Manajem has been completed a full Bankable Feasibility Study for Al Khnaiguiyah Zinc & Copper Mining Project in Cooperation with some of the biggest Technical, Consulting, Laboratories and Mining Institutes in the world, Based on the Old Exploration Data and the New Performed Exploration works at the site by Manajem with the last Three years.

  • Project Capacity: (3.000) Ton/Day
  • Concentration:

  Zinc: (7.56) %

  Copper: (0.98)%

  Gold: (0.3) g/ Ton

  Silver: (7) g/ Ton

  • Daily Production:

  (182) Ton Zinc/ Day

  (23.75) Ton Copper/ Day

  (1026.95) g Gold/ Day

           (21) Kg Silver/ Day